Nestlé video guide
- Project scope
- Installed fiber network with 300 drops, 80 cameras, and WiFi access points. Labor was 1,200 hours.
- Reported outcome
- Improved network security and production efficiency.
- Client
- Nestlé
- Location
- Bakersfield, CA
- Services
- Fiber, WiFi, Security
Project requirements
Needed 300 drops, 80 cameras, and WiFi for a secure, high-speed network.
Installation scope
Installed fiber network with 300 drops, 80 cameras, and WiFi access points. Labor was 1,200 hours.
Reported outcome
Improved network security and production efficiency.
Project details and outcomes are from the ITECH2 project summary. Source summary